Canon model VB-H610VE A&E Specifications
OWNER / May 16, 2013 28 23 00 - 18 Video Surveillance System
L. Painting
All conduit, fittings, and junction boxes shall be painted to match the existing surfaces they are
mounted on. This work may be performed after the system is fully operational.
3.03 FIELD QUALITY CONTROL
A. Final Tests & Inspection
The Contractor shall coordinate with the OWNER’s Project Manager for final tests and
inspections in the presence of the Project Manager, System Designer/Consultant, and a factory
support person from the manufacturer.
B. Training
1. The training of all personnel shall be performed on-site by the Contractor and a factory
trainer provided by the manufacturers.
2. The manufacturer shall provide a training tutorial and all handout material.
3. The manufacturer shall also supply video recording of either the actual on-site training or
a copy of in-house training at the manufacturer’s office.
END OF SECTION